A typical timeline
| Stage | What happens | Typical time |
|---|---|---|
| 1. Strip-out | Old suite, tiles and flooring removed and taken away | 1–2 days |
| 2. First fix | Plumber and electrician run new pipes and cables | 1–3 days |
| 3. Walls and floor | Boarding, plastering and repairs to the floor | 2–3 days |
| 4. Waterproofing | Shower area tanked and left to cure | 1–2 days |
| 5. Tiling | Walls and floor tiled and grouted | 3–5 days |
| 6. Second fix | Bath or shower, toilet, basin, taps and towel rail fitted | 1–2 days |
| 7. Finishing | Sealant, decorating, final checks and clean | 1–2 days |
Some stages need drying or curing time before the next one starts, so the days don't always run back to back.
What causes delays
- Hidden problems: rotten floorboards, old pipework or water damage found once the old bathroom comes out
- Products not arriving: order the suite, tiles and taps before work starts
- Changing the layout: moving the toilet or shower means extra plumbing and sometimes new drainage
- Decisions mid-job: choosing tiles or fittings after work has started
Living without a bathroom
If it's your only bathroom, ask for the toilet to be reconnected at the end of each day where possible, and plan showers at the gym, work or with family for the tiling stage.
Get a free quote
YSE Renovations manages bathroom renovations from strip-out to the final clean, bringing in a qualified plumber and electrician for those parts of the job. You get one point of contact and a written timeline before we start. We're a father-and-son team based in Colindale, covering all of London.
Call or WhatsApp 07460 351689 for a free, itemised written quote.

Painting & decorating
Wood & laminate flooring
Tiling
Rendering
Room & rental refreshes
Toilet fixes & minor repairs