Typical timings
| Property (interior) | One decorator | Two decorators |
|---|---|---|
| Single room | 1–2 days | 1 day |
| Hall, stairs and landing | 3–5 days | 2–3 days |
| 1-bed flat | 3–5 days | 2–3 days |
| 2-bed flat | 5–8 days | 3–5 days |
| 3-bed house | 7–12 days | 5–7 days |
These assume walls, ceilings and woodwork in reasonable condition, with two coats throughout.
Why it can't be rushed
Most of the time on a decorating job isn't spent painting. It's spent on:
- Protection: covering floors and furniture and masking edges
- Preparation: filling, sanding and caulking, which makes the finish last
- Drying time: filler, primer and each coat of paint need time before the next goes on
Skipping any of these is how you end up with cracks coming back or paint peeling within a year.
What makes a job take longer
- High ceilings and stairwells that need ladders or platforms
- Lots of cracks, old wallpaper or damaged plaster
- Woodwork in poor condition, or switching from gloss to a different finish
- Rooms full of furniture
- Dark colours being covered with light ones
Planning around it
We can work room by room so you can keep living in your home, and we'll give you a start date and an estimated duration in writing with your quote.
Get a free quote
YSE Renovations is a father-and-son decorating team with 20 years' experience, based in Colindale and covering all of London.
Call or WhatsApp 07460 351689 for a free, itemised written quote.

Painting & decorating
Wood & laminate flooring
Tiling
Rendering
Room & rental refreshes
Toilet fixes & minor repairs